Installation Tasks
Before starting the installation, review the following information:
Required Equipment and Tools on page 65
Warnings and Cautions on page 10
Inspecting the Equipment and Reporting Damage on page 12
Complete the Installation tasks in the following order:
Task Description Reference
1 Check the AC Supply See details on page
14
2 Customize the EPS2/EPS5 See details on page 15
3 Mount the EPS2/EPS5 in the Rack See details on page 18
4 Connect the Output Cables See details on page 21
5 Install the Batteries Modules (if required) See details on page 23
6 Mount the Battery Temperature Sensor (if required) See details on page 26
7 Connect communications cable (if required) See details on page 26
8 Connect to the AC Supply Point See details on page 28
For details of external communications refer to Communications Options in the System
Controller Operation Handbook (see Related Information on page
i).
Task 1 - Check the AC Supply
It is important that the ac supply for the Enterprise Power Solutions dc power system
includes the correct levels of protection.
Step 1 - Check the type of ac supply
Check the type of ac supply. Only the types of ac supply listed in the
Specifications on page
59 are suitable for the EPS2/EPS5.
Only use an ac supply referenced to ground, or with a protection system so
that the phase-ground voltage cannot exceed the rating of the rectifier.