Enterprise Power Solutions Installation and Operation Guide
30
Copyright © 2008 Eaton Corporation. All Rights Reserved.
IPN 997-00012-56C September 2008
Start-Up Tasks
Complete all the Installation tasks (see details on page 14) before starting these Start-Up
tasks.
Complete the Start-Up tasks in the following order:
Task Description Reference
1 Insert the Rectifiers See details on page
30
2 Complete the Pre-Power-Up Checklist See details
3 Apply AC Power See details on page 31
4 Configure the dc power system See details on page 32
5 Apply dc Power to Battery and Load See details on page 34
Task 1 - Inserting the Rectifiers
•
Do NOT install the rectifiers until the room has been cleaned and is dust free.
• Do NOT switch on the ac supply at this stage.
Step 1 - Unpack the rectifiers
Unpack the rectifiers and inspect them carefully for possible transport damage.
Report any damage immediately using a completed Equipment Incident Report
on page
71.
Keep the original packaging to return a rectifier for replacement or repair, if
required.
Step 2 - Fit first rectifier
1 Align the rectifier with the left side of the shelf.
2 Push in the rectifier until the retaining screw contacts the shelf.
3 Tighten the retaining screw to 1.5Nm (13.3 inch-pounds). This will locate the
rectifier in its rear connector.