Enterprise Power Solutions Installation and Operation Guide
50
Copyright © 2008 Eaton Corporation. All Rights Reserved.
IPN 997-00012-56C September 2008
Step 4 - Replace circuit breaker cover
Step 5 - Connect load or battery module (if required)
1 Switch the circuit breaker to the OFF (O) position.
2 Connect the load equipment or battery (if required):
For a load circuit breaker, connect the cables to the load equipment
(see details on page
21), or
For a battery circuit breaker, plug in the battery module cable (see
details on page
51).
Step 6 - Switch on circuit breaker
For a load circuit breaker:
Switch the load circuit breaker to the ON (I) position.
Follow the equipment suppliers instructions for starting the
equipment.
Check the Load Fuse Fail alarm clears.
Only load circuit breakers with equipment connected must be switched
ON (I) to clear the alarm.
For a battery circuit breaker:
Switch the battery circuit breaker to the ON (I) position.
Check the Battery Fuse Fail alarm clears.
All battery circuit breakers (including any unused circuit breakers)
must be switched ON (I) to clear the alarm.
The battery module(s) will begin to charge.
The batteries will charge to 90% capacity in approximately 3 hours.
However, it is recommended that they are charged for 24 hours after
long-term storage.
Procedure complete