2 Mechanical installation
Topics covered in this chapter:
Meter piping, lifting and mounting
Meter components
Piping recommendations
Pre-installation inspection
Mounting requirements in heated or cooled pipelines
2.1 Meter piping, lifting and mounting
Refer to the following sections for piping recommendations, lifting with hoist rings and
slings, mounting in heated or cooled pipelines and safety warnings and precautions.
CAUTION!
SURFACE TEMPERATURE HAZARD
The meter body and piping may be extremely hot or cold.
Wear appropriate personal protective equipment when coming in contact with the meter.
Failure to comply may result in injury.
WARNING!
CUTTING HAZARD
Sharp edges may be present on the meter.
Wear appropriate personal protective equipment when working on the meter. Failure to
comply may cause serious injury.
CAUTION!
TRANSPORTATION HAZARD
When moving the meter, do not insert the forks of a forklift into the bore.
Inserting the forks may cause the meter to become unstable, resulting in injury or damage to
the bore and sealing face.
Mechanical installation
Installation manual 23

Table of Contents

Other manuals for Emerson Daniel 3410 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Emerson Daniel 3410 Series and is the answer not in the manual?

Emerson Daniel 3410 Series Specifications

General IconGeneral
BrandEmerson
ModelDaniel 3410 Series
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals