Installation Liquistation CSF33
20 Endress+Hauser
Connecting the suction line on version with peristaltic pump
A0013705
10 Connecting the suction line from the side (as-delivered
state)
1 Small thread adapter nut
2 Hose
3 Thread adapter nut
4 Hose gland
A0013706
11 Suction line
1. Unscrew the thread adapter nut (item 3) and the hose fitting (item 4) from the side
panel.
2. Unscrew the small thread adapter nut (item 1) and remove the hose.
3. Connect the suction line from below as illustrated.
4. Insert the dummy plugs supplied.
5.3 Post-installation check
1. Verify that the suction line is securely connected to the device.
2. Visually check that the suction line is installed correctly from the sampling point to
the device.
3. Verify that the rotating arm is correctly engaged.
4. Allow the sampler to rest for a minimum of 12 hours following installation and
before switch-on. Otherwise you may cause damage to the climate control module.