Maintenance  8. Cable 
 
162  VT  Rev.1 
 
Grease: GPL-224 
Between Base-Arm #1  : 4.5±1g 
Between Arm #1-Arm #2  : 4.5±1g 
Between Arm #2-Arm #3  : 2.8±0.5g 
Between Arm #3-Arm #4  : 2.8±0.5g 
 evenly to the entire cable inside the sleeve and the end of the sleeve by 
the grease, be careful not to attach the grease to the AMP board. 
Connect the following connectors to 
the controller unit.
 
A: Power cable connector 
B: Signal cable connector 
C: Hand I/O connector 
D: LED connectors × 2 
the controller unit into the base. 
Insert the controller unit while moving it to 
the 
Then, gently move the plate of the 
controller
 unit to the left and let the thermal 
 contacts with the wall inside the base. 
Move it to the right to insert