STRADA PAL – MAINTENANCE MANUAL
30/149
7. PREVENTIVE MAINTENANCE PROCEDURES
7.1 Preparing a battery
This procedure must be carried out in workshop.
7.1.1 Preliminary operations
Not applicable
7.1.2 Procedure
A. To connect the 2 terminals, stack as follows (from the outside of the battery):
Screw,
Battery terminal,
Serrated washer,
Strand terminal,
Nut with serrated base.
Preparing the connections
B. Put caps on the two terminals.
C. Put a tie to waterproof the connection (as indicated on the figure below).
Waterproofing the connections (example with + red terminal)
D. Put a third tie at the base of the red terminal protection of the 42 Ah battery (as
indicated on the figure below).

Table of Contents