Multifunction PV Analyzer
Performance Tests
35
Setup #3
To veri f y :
1. Install the test lead from the AUX port to AUX LO on 552xA to make a short.
2. Clamp the current clamp around the 552xA AUX port wire.
3. Set the 552xA calibrator to output and complete test points in Ta b l e 1 3 that are provided
for Setup #3 in order of operations from the table.
4. Push OPER on the 552xA to set the operate mode, if necessary, and wait for the calibrator
to stabilize.
5. Record the voltage indication on the DMM
÷10 in the test record.
Note
This conversion only works when reading the DMM indication in millivolts, not volts.
Setup #4
To veri f y :
1. Install the test lead from 20 A port to AUX LO on the 552xA to make a short.
2. Clamp the current clamp around the 552xA port wire.
3. Set the 552xA calibrator to output and complete test points in Ta b l e 1 3 that are provided
for Setup #4 in order of operations from the table.
4. Push OPER on the 552xA to set the operate mode, if necessary, and wait for the calibrator
to stabilize.
5. Record the voltage indication on the DMM
÷10 in the test record.
Note
This conversion only works when reading the DMM indication in millivolts, not volts.