CHAPTER 4: ELECTRICAL INSTALLATION CONSIDERATIONS WHEN INSTALLING METERS
EPM 2200 POWER METER – INSTRUCTION MANUAL 4–3
Figure 4-1: CT leads terminated to meter, #8 screw for lug connection
Wiring diagrams are detailed in the diagrams shown below in this chapter.
Communications connections are detailed in Chapter 5.
4.1.2 CT Leads Pass-Through (No Meter Termination)
The second method allows the CT wires to pass through the CT Inputs without terminating
at the meter. In this case, remove the current gills and place the CT wire directly through
the CT opening. The opening will accommodate up to 0.177" / 4.5 mm maximum diameter
CT wire.
Current gills
(nickel-plated
brass stud)