Chapter 2. Installation
TransPort
®
PT900 User’s Manual 11
2.5.3 Mounting the Clamp-On Fixture (cont.)
3. Adjust the clamp-on fixture position so that the outer edge of the closest
end piece is located at the chosen distance from the nearest inlet, outlet,
joint or fitting in the pipeline (see Figure 10 below).
Figure 10: Adjusting the Fixture Position
4. Place the clamp-on fixture on top of the pipe so that minimal effort is
required to maintain its position during installation (see Figure 11 below).
Figure 11: Fixture Placed on Top of Pipe
>6”/150 mm

Table of Contents