6 Inspections
6.1 Mechanical inspections
Fig.34: Anchor point
• Check the tightening of the anchoring and connections on the terminals 2 3 and the con-
nection boxes 1 .
• Check the ground connections 2 or 3 .
Fig.35: Suspension tube and ceiling cover
• Check the rigidity of the suspension by shaking the assembly.
• Verify the verticality of the tube.
• SAT and SATX tube: Check the tightening of the screws of the half-plates on shafts 2 and 3.
• SB tube: Check the tightening of the cover split-rings 4 .
• Check that the cover and the retention and upper seals 1 are secure.
• Check the resistance of the silicone sleeve 2 and, for the modified SAT tube, the screw
cover labels 3 for shaft 2 and 3.