Startup
312062A 21
Startup
1. Load fluid with feed pumps
a. Check that all Setup steps are complete.
b. Check that inlet screens are clean before daily
startup, page 33.
c. Check level and condition of ISO lube daily,
page 32.
d. Turn on component B agitator, if used.
e. Turn both PRESSURE RELIEF/SPRAY valves
(SA, SB) to SPRAY .
f. Start feed pumps.
g. Open fluid inlet valves (FV). Check for leaks.
h. Use feed pumps to load system. Hold gun fluid
manifold over two grounded waste containers.
Open fluid valves A and B until clean, air-free
fluid comes from valves. Close valves.
Do not operate Reactor without all covers and
shrouds in place.
The Reactor is tested with oil at the factory. Flush
out the oil with a compatible solvent before spray-
ing. See page 35.
ti9877a
SA
SB
Do not mix components A and B during startup.
Always provide two grounded waste containers to
keep component A and component B fluids separate.
FV
ti10002a
ti2484a