(2)LSQWRF60VM/NaA-M, LSQWRF65VM/NaA-M (unit:mm)
5.4.2 Precautions for Installation
(1)Pipelines and electric lines should be correctly connected.
(2)Rubber pads and rubber flexible connectors should be used during installation for noise
and vibration reduction.
(3)Under subzero climate, when the heat pump runs for cooling, anti-freeze liquid is
required.
(4)Dedicated lugs should be used for lifting. During lifting, proper protection should be taken
so as to avoid pipelines from being damaged.
5.4.3 Installation Environment
(1)The unit should not be installed within 25m of the residence; otherwise a sound insulating
wall should be set up.
(2)When the unit is to be installed at the roof, the foundation should be located at the heel
posts. If the floor is quite thin, or there is VIP rooms under the floor, the spring damper is
required.
(3)Fire, inflammably, corrosive gas and waste gas should be avoided around the unit. Also,
the unit cannot be installed around the chimney and discharge fan.
(4)Ventilation should be in good condition and no air flow would be trapped.