8.1.2 Two point calibration with a micro piston pump
D A N G E R
Electrocution hazard. Always make sure the analyzer is turned off and power is disconnected
before installing this option.
To install the pump, refer to Micro piston pump on page 47.
To install the 10 liter canister, refer to Canister kit on page 48.
8.1.3 Two point calibration with a pulse pump
D A N G E R
Electrocution hazard. Always make sure the analyzer is turned off and power is disconnected
before installing this option.
To install the pump, refer to Pulse pump on page 48.
To install the 10 liter canister, refer to Canister kit on page 48.
8.2 Chemical cleaning
D A N G E R
Electrocution hazard. Always make sure the analyzer is turned off and power is disconnected
before installing this option.
This option allows the addition of a chemical cleaning solution during rinsing. The kit
includes a pump and a 10 liter canister equipped with a level detector and strainer.
Figure 12 Chemical cleaning option
1 Tygon
®
tubing 3 Plastic nipple 5 Electric cable
2 Measurement cell cover 4 Tygon
®
tubing
Install the option as follows (the numbers in brackets refer to Figure 12):
1. Install the pump on the rear of the panel (position 7 in Figure 10 on page 37).
2. Dismount the transparent cell from its cover.
3. Insert the Tygon
®
tubing (1) into one of the 5 holes in the measurement cell cover (2).
4. Insert the plastic nipple (3) into the end of the tube under the cell cover.
Additional options
39