Your Hitachi Vantara account team will assist you throughout the site planning process.
The Hitachi V
antara account team is responsible for:
Assisting you as needed to plan the installation for your specic site and operational
conguration.
Coordinating Hitachi Vantara resources to ensure smooth delivery, installation, and
conguration of the units.
Customer responsibilities
When planning and preparing for the installation of a storage system, the user assumes
the following responsibilities:
Purchase site-planning services from Hitachi Global Services.
Provide the space, people, and tools for unpacking, installing, and operating the
storage system.
Conrm that the path from where the storage system is delivered to the installation
site is large enough to support the storage system. Take into account all ramps,
walkways, and elevators and possible obstructions.
Maintain the proper environmental conditions for the storage system. For optimal
performance, storage systems require controlled environmental conditions that are
often best facilitated through raised ooring and under-oor air conditioning. It is the
responsibility of the customer to monitor this environment and ensure continued
conformance with the recommended environmental specications.
Provide adequate power facilities for the storage system. Adequate power is
necessary to ensure reliable functioning of electronic equipment and for the safety of
the customer's installation. The customer is responsible for procuring, installing, and
maintaining adequate power to the equipment.
Supply the network connections and external cabling required by the storage system.
Delivery space requirements
Verify that the delivery area, the destination, and the path between them meet the
standard delivery clearance and weight requirements of the storage system.
The delivery area must provide enough space and floor strength to support the
packaged equipment cartons for the storage system. Doorways and hallways must
provide enough clearance to move the equipment safely from the delivery area to the
destination. Permanent obstructions such as pillars or narrow doorways can cause
equipment damage. If necessary, plan for the removal of walls or doors.
Verify that all floors, stairs, and elevators you use when moving the storage system to its
destination can support the weight and size of the equipment. Failure to do so could
damage the equipment or your site.
Climatization
Storage systems that are shipped or stored at extreme temperatures require time to
adjust to operating temperatures before startup.
Customer responsibilities
Chapter 1: Installation site considerations
Site Preparation Guide for VSP G/F350, G/F370, G/F700, G/F900 11

Other manuals for Hitachi Virtual Storage Platform F350

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Hitachi Virtual Storage Platform F350 and is the answer not in the manual?

Hitachi Virtual Storage Platform F350 Specifications

General IconGeneral
BrandHitachi
ModelVirtual Storage Platform F350
CategoryStorage
LanguageEnglish

Related product manuals