Appendix A: Site preparation checklist
Verify the availability of each item in the site preparation checklist.
The following tasks might require several weeks to complete:
Acquiring required power outlets.
Arranging for an electrician.
Adding or modifying air conditioning systems.
Making room alterations to accommodate the storage system.
Ordering third-party equipment, such as non-Hitachi racks, network switches, and
host computers to support the Hitachi VSP storage system.
Checklist questions Yes No
Safety
Is the computer room free
of any equipment servicing
hazar
ds, such as electrical
or data cables that obstruct
access?
Does the computer room
have a re-protection
system?
Computer room space planning
Does the existing oor plan
need to be revised to
include the storage
system?
Does the oor plan include
the clearance required for
the oor's load rating?
Does the oor plan include
adequate space for airow
and servicing needs?
Computer room infrastructure
Appendix A: Site preparation checklist
Site Preparation Guide for VSP G/F350, G/F370, G/F700, G/F900 50

Other manuals for Hitachi Virtual Storage Platform F350

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Hitachi Virtual Storage Platform F350 and is the answer not in the manual?

Hitachi Virtual Storage Platform F350 Specifications

General IconGeneral
BrandHitachi
ModelVirtual Storage Platform F350
CategoryStorage
LanguageEnglish

Related product manuals