ID3000 Series Installation & Commissioning Manual
Contents
ii
997-274-000-6, Issue 6
September 2009
Contents
1 Introduction 1
1.1 CE Marking 1
1.2 System Design and Planning 1
1.3 Personnel 1
1.4 General 1
1.5 Date-dependent Functions 2
Installation: Sections 2-6
2 Installation Guide 3
2.1 How to Use this Guide 3
2.1.1 Related Documents 3
2.1.2 Warnings and Cautions 3
2.1.3 Tips 3
2.1.4 Glossary of Icons 4
2.2 Pre-Installation Check List 5
2.2.1 Some DO’s and DONT’s 5
2.3 Transient Protection 6
2.4 Installation 7
2.4.1 Checking Your Panel for Damage 7
2.4.2 What to do if Your Module is Damaged 8
2.4.3 Back Box Fixing 9
2.4.4 Electronics Modules 10
2.5 Replacing the Electronics Modules 11
2.6 Flush Mounting Bezel (Optional) 11
2.7 Moulded Front Covers 12
3 Cabling 14
3.1 Cabling Instructions 14
3.1.1 Cable Terminations 15
3.2 Cable Installation Notes 16
3.2.1 Introduction 16
3.2.2 Quality of Cable and of Cable Installation 16
3.3 EMC Considerations 17
3.3.1 Screen Termination 17
3.3.2 Ferrite Sleeves (Optional) 17
3.4 MICC Cables 17
WARNING: Risk of electric shock. Before
working on mains connections, ensure
mains power supply to the panel is
disconnected.
CAUTION: Refer to the accompanying
documentation. (When used in the
documentation, this marking is normally
associated with additional instructions).’
The following markings are used either on
the panel hardware or in the
documentation. They have the following
meaning: