5. Close the cable clamps.
6. Verify that the peripheral cables and power cords are secured properly.
Two people is needed for this procedure:Two people is needed for this procedure: one to slide the server in and out of the rack, and the other to observe the peripheral cables
and power cords.
a. Fully extend the server tray out of the rack.
b. Make sure that there is enough slack in the cables and cords for a full extension of the rack rails.
Make sure that there is no cable binding or crimping.
c. Slide the server tray in and out of the rack to verify that there is no risk of accidental disconnection of the peripheral cables and
power cords.
7. Tighten the server tray thumbscrews.