• Hardware documentation and software products
• Rack-mounting hardware and documentation
You might also need the following items:
• Operating system or application software
• Hardware options
• Screwdrivers
◦ T-10 Torx
◦ T-15 Torx
◦ T-30 Torx
Installation overview
Installation of a server requires the following steps:
Procedure
1. Install the chassis into the rack (Installing the chassis into the rack on page 32).
2. Install any server options. (Installing hardware options on page 39).
3. Install the operating system (Operating system on page 39).
4. Install system software.
5. Register the server (Registering the server on page 40).
Installing the chassis into the rack
CAUTION: Always plan the rack installation so that the heaviest item is on the bottom of the rack. Install
the heaviest item first, and continue to populate the rack from the bottom to the top.
Prerequisites
Before installing the chassis, observe all necessary warnings and cautions.
Procedure
1. Unpack the system and remove all components from the chassis.
2. Install the chassis and cable management arm into the rack. For more information, see the installation
instructions that ship with the selected rail system.
3. Install options in the chassis.
4. Install all components in their original locations in the chassis.
5. Connect the power cords to the rear of the chassis.
6. Connect the system to the power source.
32 Installation overview