Figure 4-14 Securing the base support
After the base support is secured, verify the installation to ensure normal use of
the base support and smooth subsequent installation.
Table 4-4 Verifying the installation
Check Item Check Method Criteria
Bolts and nuts Tighten the bolts and nuts
again using a wrench to the
same torque.
Bolts and nuts are
tightened.
Step 5 Install the rst Smart PCS.
Move the Smart PCS to the top of the base support, push it along the guide rails
from the DC side, and secure it to the base support using the delivered screws.
Both the DC and AC sides need to be secured.
Do not stand on the top of the base support.
Figure 4-15 Securing a Smart PCS