Table 21. CA000000 to CA2799FF checkpoints (continued)
v If the system hangs on a progress code, follow the suggested actions in the order in which they are listed in
the Action column until the problem is solved. If an action solves the problem, you can stop performing the
remaining actions.
v See Chapter 3, “Parts listing, Type 8406,” on page 229 to determine which components are CRUs and which
components are FRUs.
Progress code Description Action
CA00E153 End adapter FCODE probing and
evaluation
1. Go to “Checkout procedure” on page 184.
2. Replace the system-board, as described in
“Replacing the FRU system-board and
chassis assembly” on page 260.
CA00E154 Create PCI bridge node
1. Go to “Checkout procedure” on page 184.
2. Replace the system-board, as described in
“Replacing the FRU system-board and
chassis assembly” on page 260.
CA00E155 Probing PCI bridge secondary bus
1. Go to “Checkout procedure” on page 184.
2. Replace the system-board, as described in
“Replacing the FRU system-board and
chassis assembly” on page 260.
CA00E156 Create plug-in PCI bridge node
1. Go to “Checkout procedure” on page 184.
2. Replace the system-board, as described in
“Replacing the FRU system-board and
chassis assembly” on page 260.
CA00E15B Transfer control to operating system
(service mode boot)
Go to “Boot problem resolution” on page 190.
CA00E15F Adapter VPD evaluation
1. Go to “Checkout procedure” on page 184.
2. Replace the system-board, as described in
“Replacing the FRU system-board and
chassis assembly” on page 260.
CA00E170 Start of PCI bus probe
1. Go to “Checkout procedure” on page 184.
2. Replace the system-board, as described in
“Replacing the FRU system-board and
chassis assembly” on page 260.
CA00E172 First pass of PCI device probe
1. Go to “Checkout procedure” on page 184.
2. Replace the system-board, as described in
“Replacing the FRU system-board and
chassis assembly” on page 260.
CA00E174 Establishing host connection
1. Verify that:
v The bootp server is correctly configured;
then, retry the operation.
v The network connections are correct;
then, retry the operation.
2. If the problem persists:
a. Go to “Checkout procedure” on page
184.
b. Replace the system-board, as described
in “Replacing the FRU system-board
and chassis assembly” on page 260.
Chapter 2. Diagnostics 109