AC Drive Installation
‑17‑
4.3 Guide Rail Installation
Install the guide rail for T1 models (three‑phase 380‑480 V: 0.37‑2.2 kW; single‑phase
200‑240 V: 0.37‑1.5 kW). For T2 models (three‑phase 380‑480 V: 4‑5.5 kW; single‑phase
200‑240 V: 2.2 kW), the guide rail is not required.
PPrreerreeqquuiissiitteess
● To install the AC drive with the guide rail, prepare the DIN guide rail (option). For
details, see "List of Options" in
MD600 Series Basic AC Drive Hardware Guide
.
● Before installation, check that the installation tools and environment have been
prepared. For details, see "Mechanical Design" in the
MD600 Series Basic AC Drive
Hardware Guide
. This section describes quick guide rail steps.
PPrroocceedduurree
1. Insert the guide rail latch into the slot at the bottom of the drive until it clicks into
place, as shown in ①.
Figure ② shows that the guide rail is installed in place.
Scenario 1: The guide rail is not installed in the cabinet.
2. Use the straight screwdriver to pull the guide rail latch up slightly, as shown in ③.
3. Install the guide rail to the snap‑fit joint on the drive, as shown in ④.
4. Press the guide rail latch down to the place to lock the guide rail, as shown in ⑤.
Scenario 2: The guide rail is installed in the cabinet.
5. Hold the drive at the fixing position, push the bottom of the drive in the direction of
the arrow to the place to lock it to the snap‑fit joint, as shown in ⑥.
6. Press the guide rail latch down to the place to lock the guide rail, as shown in ⑦.