AC Drive Installation
‑18‑
Figure 4‑1 Guide rail installation
4.4 Post-installation Inspection
After the installation is done, check the following items.
Table 4–2 Post‑installation checklist
No. Item
Checked
1
The ceiling height meets the minimum requirements for smooth
ventilation. The air inlet and air outlet are free of obstruction and
have sufficient space. Sufficient space is reserved for safe passing
when the cabinet door is opened.
□
2
All contact protection devices (such as the guard plate) inside and
outside the cabinet are installed.
□