EasyManuals Logo

IVT Greenline HC 22 User Manual

IVT Greenline HC 22
112 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #28 background imageLoading...
Page #28 background image
Installation
6 720 645 504 (2011/04) en
28
The following description of filling presupposes the use
of the filling station accessory. Follow corresponding
steps if other equipment is used.
Fig. 15 Example of a filling unit
B Connect two hoses from the filling station to the
filling unit ( Figure 16).
Fig. 16 Filling with filling station
B Fill the filling station with collector circuit fluid. Fill
water before you fill antifreeze.
B Turn the valves on the filling unit so that they are in
filling position ( Figure 17).
Fig. 17 Filling unit in filling position
B Turn the valves on the filling station so that they are
in mixing position ( Figure 18).
Fig. 18 Filling station in mixing position
B Start the filling station (pump) and mix the collector
circuit fluid for at least two minutes.
B Turn the valves on the filling station to filling position
and fill the circuit with collector circuit fluid
( Figure 19).
Fig. 19 Filling unit in filling position
Double U pipes, each of which consists of
two descending and two ascending pipes,
are most often used as a rock collector.
6720614967-32.1I
Repeat the following steps for each circuit.
One circuit at a time is filled with collector
circuit fluid. Keep the valves closed in the
other loops during the process.
6720614967-35.1I

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IVT Greenline HC 22 and is the answer not in the manual?

IVT Greenline HC 22 Specifications

General IconGeneral
BrandIVT
ModelGreenline HC 22
CategoryHeat Pump
LanguageEnglish

Related product manuals