144
POWERHEAD
INSTALLATION
Apply Gasket Sealing Compound to the six pow-
erhead retaining screws and install the screws.
Tighten the six powerhead retaining screws and
torque 60 to 84 in. lbs. (7 to 9 N·m).
IMPORTANT: Adjust the start button assembly.
See Start Switch on p. 126. To avoid permanent
powerhead damage, instruct operator to repeat
the original outboard break-in procedure as
described in the Operator’s Guide.
1. Lower crankcase head
2. Long water tube
3. Short water tube
32401
1. Long water tube opening
2. Short water tube opening
32398
3
2
1
2
1
32309