C
irculating Valve
D
istributor Valve
TACK DISTRIBUTOR
19
TACK DISTRIBUTOR
OPERATION OF SPRAY WAND AND SPRAY BAR
17. Back flush:
Open circulating valve to let material flow back into tank.
C
lose tack valve at bottom of tank.
Push in distributor valve to retrieve material out of hose.
18. Wand:
Open spray wand valve and allow 30 seconds before flushing.
19. Spray bar:
Open spray bar select valve.
Allow 30 seconds then close nozzle valve closest to center of spray bar.
Allow 10 seconds then close the next valve towards outside of spray bar.
Repeat until all nozzles are flush.
Flushing spray wand:
Close the circulating valve.
Close the valve on the wand.
Open the wand select.
Pull out distributor valve knob.
Open flush valve on hose coming out of flush tank.
Open valve on wand and flush until you see flush material.
Close valve on wand, and shutdown engine.
Check all valves on machine to make sure they are all closed.
Flushing spray bar:
Close the circulating valve on tank.
Open spraybar select valve to let material flow to bars.
Pull out distributor valve knob.
Open flush valve to let flush material go to spray bar.
Open all nozzle valves one at a time, until flush material is visible; then close valves.
Shut down engine and make sure all valves are shut.
20. Height of the Spray Bar may be adjusted by removing two bolts and raising or lowering the bar to
desired height.
21. Six Spray Nozzles may be turned off or on individually or the entire bar may turned off or on through
one v
alve.
NOTE: When moving from one job site to another, turn the individual nozzle valves off to
prevent dripping.