Commissioning
Operang Instrucons i510 protec 17
7 Commissioning
7.1 Inialswitch-on
DANGER
Electrical voltage
Incorrect wiring can cause unexpected states during the
commissioning phase.
Wiring must be complete and correct.
Wiring must be free of short circuits and earth faults.
The motor circuit conguraon (star/delta) must be adapted to the
inverter.
The motor must be connected in-phase (rotang direcon).
The "emergency o" funcon of the overall system must operate
correctly.
Clear hazardous area.
Observe safety instrucons and safety clearances.
Precondions
The power connecons must be wired.
The digital inputs must be wired:
X3/DI1 (start/stop),
X3/DI3 (reversal),
X3/DI4 (frequency preset 20 Hz)
The analog input X3/AI1 must not be wired or connected to GND.
Switching on mains voltage
1. Switch on mains voltage.
2. Check readiness for operaon.
3. Observe LED status displays “RDY” and “ERR” on the inverter
front panel.
See „LED status.
28
7.2 Keypad module
The inverter i510 protec comes with permanently installed keypad.

Related product manuals