For additional information, see the complete installation and operation guide at www.lutron.com/qs
GRAFIK Eye QS with DALI® Control Unit Quick Installation and Operation Guide
6
Note: Use appropriate wire connecting devices as specified by local codes.
* Do not connect terminal 2 between any GRAFIK Eye QS control unit and any other power supply,
including another GRAFIK Eye QS control unit.
See “Power Group Wiring” for a detailed wiring example.
Wiring the GRAFIK Eye QS with DALI® Control Unit:
Overview of IEC PELV Wiring
IR Wiring
1: IR DATA
2: IR COM
From external IR
connection (by others)
1.0 mm
2
each terminal
1234
1: COM
2: 24 V-*
3: MUX
4: MUX
To control stations,
window treatments,
or other
GRAFIK Eye QS
control units
QS Link Control Wiring
24 V- 100 mA
Common and power
(terminals 1 and 2)
Two 1.0 mm
2
each terminal
Data
(terminals 3 and 4)
Twisted, shielded pair 0.5 mm
2
each terminal
Contact Closure Input Wiring
24 V- 50 mA
For settings, see the full installation and
operation guide at www.lutron.com/qs
ABC
Example: Occupancy sensor (maximum 1)
A: CCI SIG
B: 24 V-
C: CCI COM
1.0 mm
2
each terminal