For additional information, see the complete installation and operation guide at www.lutron.com/qs
GRAFIK Eye QS with DALI® Control Unit Quick Installation and Operation Guide
9
Completing Installation of the GRAFIK Eye QS with DALI® Control Unit
1. Mount the control unit in the wallbox as
shown using the four screws provided.
Note: Follow all local and national electrical
codes when installing IECPELV/
NEC® Class 2 wiring with line
voltage/mains wiring.
2. Verify installation:
• Restore power.
• Press the top scene button. The LED will
light.
• Press the zone raise and lower buttons.
Make sure the control unit is dimming all
connected loads.
3. Apply the protective overlay to the control
unit.
Wall
87 mm
95 mm
200 mm
Protective overlay
(apply after installation)
Note: When tightening mounting
screws, make sure that the hinged
cover and faceplate will open fully,
as shown.