15
1.4 Use a spirit level and pencil to mark
the route of the hot and cold water
supply pipes at 153 mm centres.
Note! The Combiflow is supplied with
inlet connections hot left, cold right
and bottom outlet as standard. For
installations with reversed hot and
cold supplies a reversed
temperature lever will be required.
Available from Kohler Mira
Customer Services. It is therefore
recommended that the correct pipe
orientation is achieved.
1.5 Remove the plaster and brick/block to
the required depth to conceal the
pipework.
Note! Depth must be sufficient to
prevent pipe concealing plates fouling
on the plumbing elbows.
1.6 Install the supply pipes. The pipes
must project 18 mm from the finished
surface of the wall at 153 mm centres.
Use the installation template to make
sure that the pipes are in the right
position.
1.7 Finish the surface of the wall as
required. The recesses from which the
pipes emerge must also
accommodate the 32 mm diameter x
10 mm deep flanges on the pipe
concealing plates.
1.8 Fit the pipe concealing plates over the
hot and cold supply pipes.
18 mm from
finished wall
surface
Centres 153 mm
Concealing Plates
32 mm
10 mm minimum
between elbow and
finished wall surface.
Circular
Recess
Elbow
For latest prices and delivery to your door visit MyTub Ltd 0845 303 8383 www.mytub.co.uk