A-1
Appendix A
Check List
Before applying power to the Chillgard RT Refrigerant Monitor, check
for all items in the following table:
ITEM CHECK FOR: CHECKED OR
INITI
ALED
1 Proper mounting of Chillgard RT Refrigerant Monitor on
a non-vibrating surface which does not block the front
panel.
Mounting must be away from direct solar heating.
2 Correct electrical connections and wiring to Chillgard RT
Refrigerant Monitor. Wiring must be done for proper
voltage.
3
4 Removal of all caps and plugs at sample line inlets
and
exhaust.
5
7 Possession of proper calibration kit and check gases
for cal
ibration.
8 An established routine calibration schedule.
Proper tubing for sample line.
Disabling of unused sampling points.
Proper end-of-line filters installed.
6