4.2 COMMISSIONING
The last step in the installation process is commissioning the meter. Commissioning is a 2 step
process. The rst step is to review the mechanical installation to conrm that the ow meter is
properly located in the piping system. The second step is a review of the meter program settings.
Both steps must be completed in order to nish the installation. A simple commissioning
checklist is shown below. A copy of this may be found online at www.onicon.com/F-4600.html.
Commissioning Checklist
Part 1 Mechanical installation
Conrm that the ow sensor is properly located in the piping system (Sec. 3.1 & 3.2).
Conrm that the ow sensor is properly oriented with respect to ow direction (Sec. 3.2).
Part 2 Programming
Verify that the Units of Measure Settings in the meter are correct (Sec. 4.1).
Conrm that there are no alarm indications and the meter is functional (Sec. 4.1.2).
4.2.1 Commissioning Following Initial Power-up
During initial power-up, the following display pages will appear when the commissioning
option is selected. The settings shown on the following page allow the installer to set
MODBUS
®
or BACnet
®
parameters, and the date and time. If the factory pre-programmed
engineering units for ow and temperature are correct, press SAVE to exit commissioning
once the correct date has been set. Momentarily press NEXT if you wish access the
remaining commissioning mode display pages as shown.