33
Maintenance 8
Maintenance of the Opsis LD500 system should be scheduled and followed on a regular
basis to ensure proper operations and prevent the possibility of malfunctions. Maintenance
records should be kept in a log book at the monitoring location.
8.1 Check list for preventive
maintenance
The following actions should be taken once a week:
Make a System check. All parameter values must be within their permissible lim-
its. See the LD500 Analyser Reference Manual for explanations.
Check the recorded light levels. If the levels have dropped, check the windows of
the light path and the alignment. Clean and adjust if necessary.
Check the standard deviations.
Once per month the following should be performed:
Backup of data from the hard disk.
Visual inspection of the system; the emitter, the receiver, the optical fibres.
Inspection and control of purge air systems.
Cleaning of windows if necessary.
Once per year:
Span calibration.
Fill up the gas inside the wavelength reference cell.
Examine the complete system, including re-certification of all test gases.