First commissioning
Operating Manual PSEN sc B 5 Series
1004508-EN-02
47
9 First commissioning
9.1 Requirements for commissioning
Please note:
} Ensure that the window of the safety laser scanner is clean, intact and without finger-
prints.
CAUTION!
Detection of violations of the protected field deteriorates
If the safety laser scanner is commissioned in other conditions, the detec-
tion of violations of the protected field may deteriorate.
Ensure that the conditions for commissioning are met.
9.2 System connection
Make sure that the selected evaluation device has the following property:
} OSSD signals are evaluated through 2 channels with feasibility monitoring
7
5
6
0 V24 V
0 V
OSSD 1
OSSD 2
24 V
0 V
1
2 24 V
F.E.8
PSENscan
4 n.c.
3
n.c.
Evaluation device
Input circuit
External
supply voltage
Warning message
Indicator light unit
Fig.: Dual-channel connection of the safety laser scanner on the input circuit of an evaluation device
(1 zone set, warning message, automatic restart)