Hardware Installation and Reference Guide Appendix E Site Selection
78
Appendix E Site Selection
The machine room should be at least 5km away from the heavy pollution source such as the
smelter, coal mine and thermal power plant, 3.7km away from the medium pollution source such as the
chemical industry, rubber industry and electroplating industry, and 2km away from the light pollution
source such as the food manufacturer and leather plant. If the pollution source is unavoidable, the
machine room should be located on the windward side of the pollution source perennially with
advanced protection.
The machine room should be at least 3.7km away from the sea or salt lake. Otherwise, the
machine room must be sealed, with air conditioner installed for temperature control. Saline soil cannot
be used for construction. Otherwise, you should select devices with advanced protection against severe
environment.
Do not build the machine room in the proximity of livestock farms. Otherwise, the machine room
should be located on the windward side of the pollution source perennially. The previous livestock
house or fertilizer warehouse cannot be used as the machine room.
The machine room should be firm enough to withstand severe weather conditions such as
windstorm and heavy rain as well as away from dust. If the dust is unavoidable, keep the door and
window away from the pollution source.
The machine room should be away from the residential area. Otherwise, the machine room should
meet the construction standard in terms of noise.
Make sure the air vent of the machine room is away from the sewage pipe, septic tank, and
sewage treatment tank. Keep the machine room under positive pressure to prevent corrosive gas from
entering the machine room to corrode components and circuit boards. Keep the machine room away
from industrial boiler and heating boiler.
The machine room had better be on the second floor or above. Otherwise, the machine room floor
should be 600mm higher than the highest flood level ever recorded.
Make sure there are no cracks or holes in the wall and floor. If there are cable entries in the wall or
window, take proper sealing measures. Ensure that the wall is flat, wear-resistant, and dust-free, which
should be up to the standard for flame retarding, soundproofing, heat absorption, dust reduction, and
electromagnetic shielding.
Keep the door and the window closed to make the machine room sealed.
The steel door is recommended for soundproofing.
Sulfur-containing materials are forbidden.
Pay attention to the location of the air conditioner. Keep the air conditioner from blowing wind
straight toward the device or blowing water drops from the window or air vent toward the device.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Ruijie RG-S5750-H Series and is the answer not in the manual?

Ruijie RG-S5750-H Series Specifications

General IconGeneral
BrandRuijie
ModelRG-S5750-H Series
CategorySwitch
LanguageEnglish

Related product manuals