Storage, Preservation – “lay-up” procedure
WP33L_BA_K1_12_en_08.fm
75
9. Wait until oil mist comes out of the final pressure line.
10. Stop compressor.
11. Install the air intake filter and the safety valve. Use new O-ring
for the safety valve.
12. If necassary post a sign that the compressor has been trea-
ted with anti-corrosion and is shut down.
13. If necessary disconnect main supply.
Restarting 1. As necessary connect the mains supply.
2. Fill compressor oil as described in chapter 5.5 "Filling Oil“.
3. Proceed as described in chapter 6.3 "Commissioning”.
preservation oil
1
st
stage