Testing the Installation
Disconnect the releasing solenoid from the fire control panel circuit before applying power. This step physically
isolates the releasing solenoid from the fire control panel and prevents accidental discharge of the releasing agent
.
To test the installation of the Shield A-XT Releasing Fire Control Panel:
1 Disconnect wiring from the EXTING. terminals to the releasing solenoid before applying power from the source.
Do not disconnect the EOL diode from the releasing solenoid.
2 Apply power to the fire control panel from the source.
3 Confirm that the Power On lamp on the fascia is illuminated.
4 Confirm that the fire control panel is not reporting trouble conditions.
Correct conflicts before proceeding with the testing if trouble conditions are reported by the fire control panel.
Once the fire control panel is trouble free, it can be configured and tested to ensure that it operates as
configured.
5 Reconnect the releasing solenoid to the EXTING. terminals of the fire control panel after the completion of
successful testing.