Installing the AC Input Fuse
To install the AC Input Fuse:
Replacing Cabinet Components
Reference General Wiring Information when replacing components of the Shield A-XT Releasing
Fire Control Panel.
1 Confirm that cabling connections at the EXTING. terminals are disconnected.
2 Confirm that 115 VAC or 230 VAC is turned-off at the power source.
3 Install the replacement fuse in the terminal block housing.
4 Re-connect cabling to the EXTING. terminals of the Shield A-XT Releasing Fire Control Panel.
5 Close and lock the door of the Shield A-XT Releasing Fire Control Panel.
6 Turn on 115 VAC or 230 VAC at the power source.
7 Test the fire control panel by operating it to determine that it functions.