Commissioning
7.1 Measures before commissioning
Standard motors SH 63 ... 355
Operating Instructions, 12/2018, A5E38483075A
81
Checks before the first test run
Before the first test run, carry out the following checks:
● The external fan is correctly fitted and aligned.
● The rotor runs freely.
● All of the retaining elements and electrical connections are securely tightened.
● The grounding and equipotential bonding connections to the mains have been correctly
made.
● The air flow is not impeded or shut off by flaps, covers or similar.
● If the cooling air is in open circulation, it has only weak, chemically abrasive properties
and a low dust content.
● All protection measures have been taken to prevent accidental contact with moving or live
parts.
Performing the test run
1. Switch the external fan motor on and off briefly.
2. Compare the direction of rotation of the external fan with the specified direction of
rotation. The direction of rotation of the external fan is indicated with an arrow on the fan
cover specifying the direction of rotation or with a terminal designation on the rating plate
of the external fan unit.
Depending on the version, the fan impeller is visible through the air inlet opening in the
fan cover on the external fan motor.
3. If the direction of rotation is wrong, then interchange two line cables in the external fan
motor terminal box.
Note
Use these operating instructions f
or motors with external fans.
7.1.7 Further documents
Note
Further documents
Observe all of the other documents provided with this machine.