Configuring the Inline Meter Connection using the SetApp Device Manager
To configure the inline meter for Energy Net communication using the SetApp
Device Manager:
1. From the SetApp Commissioning menu, select Device Manager.
2. From the Device Manager's New Devices page, select Inline Meter >> Configure.
3. Select Meter Function, and choose one of the options listed in step 5 of
To
configure the inline meter for RS485 communication using SetApp:
on page 28. If
the "Production" function was selected, enter the Serial Number of the inverter to
be metered.
4. Select AC-Grid Connection (Top / Bottom), and specify whether AC inputs are
connected to the upper terminal blocks or the bottom terminal blocks.
5. To complete the configuration, select Set and View Status to view inline meter
status details.
Notes:
During the SetApp Device Manager's operation, the inline meter's blue LED will blink
rapidly, signaling that the meter is being configured.
If the AC grid is connected to the upper terminal blocks, the meter accuracy is 1%
(Class B). If the AC grid is connected to the lower terminal blocks, the meter
accuracy is 2% (Class A).
Once powered on, the inline meter will search for an Energy Net network to join, for
up to 48 hours. After 48 hours, the meter will stop searching for a network. Push the
Up and Down buttons simultaneously for 5 seconds in order to initiate another
search session.
Push the Up and Down buttons simultaneously for 5 seconds in the following cases:
When a new communications board is installed in the inverter
When connecting to a new inverter
When switching from RS485 configuration to Energy Net
To switch connectivity from RS485 to Energy Net, use SetApp to remove the RS485
meter from the connected device list. Push the Up and Down buttons
simultaneously for 5 seconds in order to initiate Energy Net search session. Use the
SetApp Device Manager to connect the meter to the inverter (see
To
configure the
Chapter 3: Configuration 29
Inline Energy Meter with SolarEdge Energy Net Communications

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SolarEdge Inline Energy Meter and is the answer not in the manual?

SolarEdge Inline Energy Meter Specifications

General IconGeneral
BrandSolarEdge
ModelInline Energy Meter
CategoryInverter
LanguageEnglish

Related product manuals