Communication
Communication settings can be configured only after communication connections are
complete. Refer to
Setting Up Communication with the Monitoring Platform
on page 61.
From the Commissioning menu, select Monitoring Communication > Auto Select.
SetApp will automatically detect your connection method. Follow the on-screen
instructions to complete the configuration and establish communication with the
monitoring platform.
From the Commissioning menu, Select Site Communication to configure
communication between multiple SolarEdge devices or external non SolarEdge
devices, such as batteries or data loggers.
For more information on the Monitoring Platform, refer to "The Monitoring
Platform" section and to the Monitoring Platform web page at:
https://www.solaredge.com/products/pv-monitoring#/
Power Control
Power control options are detailed in the
Power Control Application Note
, available on
the SolarEdge website at: https://www.solaredge.com/sites/default/files/application_
note_power_control_configuration.pdf.
For P(Q) diagram refer to: https://www.solaredge.com/sites/default/files/application_
note_p_q_diagram_of_se_inverters_en_and_na.pdf.
NOTE
SolarEdge inverters with “Grid Support” functionality (as marked on the
inverter certification label), are compliant with UL1741 Supplement A. The
functionality is built into the inverter and no additional external device is
required.
Step 3: Verifying Proper Activation and
Commissioning
1. Select Information and verify that the correct firmware versions are installed on
each inverter.
2. Select Status and verify that inverter is operating and producing power.
3. Verify that additional configurations were properly set by viewing the relevant
Status screens.
4. Verify that the green inverter LEDis steadily lit.
Your SolarEdge power harvesting system is now operational.
Chapter 6: Activating, Commissioning and Configuring the System79
Three Phase Inverters with Synergy Technology PN: SExxK-xxxxIxxxx

Table of Contents

Other manuals for SolarEdge SE K Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SolarEdge SE K Series and is the answer not in the manual?

SolarEdge SE K Series Specifications

General IconGeneral
BrandSolarEdge
ModelSE K Series
CategoryInverter
LanguageEnglish

Related product manuals