8999151EN: v1 11/03/2021
34
Original instructions (ENGLISH)
Website: www.spearheadmachinery.com
3 Machine Preparation
3.1 Lifting The Machine
WARNING! Do not lift by headstock alone. Damage may occur which will invalidate warranty. Use
recommended lifting point locations.
Multicut 300 machines should be lifted using the four designated lifting loops in each of the four corners of the
machine deck; as shown in Figure 3.1.
Figure 3.1 Shipping Position – Multicut 300
Ensure that the machine is guided by personnel when positioning the machine to where it is required to be
placed. This is to ensure that the machine and/or equipment/personnel do not get hit by the machine.
Ensure that wherever the machine is going to be positioned afterwards is sturdy and level, so that the machine
does not end up becoming unstable and will potentially move or fall over. Consider supporting the machine with
additional chocks to ensure it remains stationary.
3.2 Post-delivery/First Use Inspection
3.2.1 Tractor Inspection
It is important to read the tractor manufacturer’s operators manual to ensure that a complete inspection to the
manufacturer’s recommendations is carried out on the tractor ensuring it is in correct working condition and has
the correct safety measures in place for use. It is important before use to check the suitability of the tractor using
the manufacturer’s manual to ensure it meets the requirements to fit and operate correctly with the machine.
3.2.2 Machine Adjustment
The machine when received from Spearhead is virtually complete and components are set correctly, requiring
minimum time to ready the machine for use. Spearhead machines are tested after manufacture.