Page 22 of 35 Document No: 9961 Revision: F Issue Date: Jan-29-2018
This document and all copies are the property of Spider
®
. All dimensions and data are indicative only.
The user must ensure that the equipment complies with local rules and regulations.
= Inspect
= Verify
= Perform process
Perform all daily tests to ensure correct operation! Do not use the
hoist for lifting until it has successfully completed the daily tests.
The following tests must be performed at the start of each work shift. If the hoist fails any test,
. Refer to the pictures on Pages 18 through 20 to identify
components. All tests are performed at or near ground level.
Before operating the hoist, inspect the following:
Wire rope
Power supply
Rigging
Platform
Hoist
Verify that all parts are present, in proper working order, and are not damaged.
Bolts, nuts, and clamps must be well secured.
Ensure the hoist is secured to the stirrup with SAE Grade 5 fasteners and locknuts that are properly
installed.
When using the hoist in a dirty environment that contains epoxy, paint, cement, sand blast
residue, or corrosive material, inspect the operation of the secondary overspeed brake several times a
day. Protective hoist covers are recommended in these environments. Contact your hoist supplier.