Before First Startup Clean Pump and Piping
Disassemble the pump and clean all product contact parts and seal parts
prior to the first operation. Follow the instructions in the “Cleaning Safety
Procedures,” below and “Routine Maintenance” on page 32. Thoroughly
clean the pump of any materials which could have accumulated during
installation.
Cleaning Safety
Procedures
Manual Cleaning
Address the following recommendations when manually cleaning your
pump:
• Do not use toxic and/or flammable solvents.
• Lock out electrical power and shut off all air prior to cleaning the
equipm
ent.
• Keep electrical panel covers closed and power off when washing the
equipmen
t.
WARNING:
To prevent an accidental start-up, lock out the power
source with lock and key.
• Clean up spills as soon as possible.
• Never attempt to clean the equipment while it is operating.
• Wear proper protective clothing.
Cleaning-In-Place (CIP)
When performing CIP:
1. Make certain that all connections in th
e cleaning circuit are properly
applied and tight to avoid contact with hot water or cleaning solutions.
2. When the cleaning cycle is controlled from a remote or automated
clea
ning center, establish safe procedures to avoid automatic start-up
while servicing equipment in the circuit.
NOTE: Always re
place the o-rings when reassembling the pump. If the
area behind these seals becomes soiled, contact WCB Application Engi-
neering for a specific cleaning and sanitizing
procedure validated to
remove bacteria.