Network Meter Block Installation, Operation, & Maintenance Manual
Maintenance 42
8. Securely reattach the back cover of the NMB with the three screws.
9. Re-mount the NMB back to its original position and restore the removed cables to the same positions.
10. Restore power to the NMB. The time will automatically be set from the NTP servers (see Section 2.2:
Real-Time Clock Synchronization).