Installation Procedure Checklist
LOH0………………..
Installation Engineer to tick complete as each task done
Task Installer Installer’s
Mate
Complete
Carry out Risk assessment / Dust Sheets /
Danger Signs on Upstairs Door
Cut / Check Aperture construction and size
Check ceiling heights upstairs and down
Confirm Pump and call station positions with
user
Fit Aperture liner
Fit Pump and trunking to LH guide.
Run Trailing Cables/Earth Wire and hose and
wire up powerpack end / Fit call stations with
screws.
Check floor levels and pack up base plate if
necessary
Install lower guides. (Ensure board over the
aperture)
Fit 2 Rollers into RH guide and clamp just below
lower liner. Place lower lateral roller/Switch
assembly and mid sling roller at bottom of guide
(see manual for order of fit). Be careful not to
damage switch assembly when installing sling.
If LONG SLING – fit intermediate guides and
brace fish cross bar below aperture to wall
Fit middle and lower control tubes/trays. Refer to
the manual.
Fit trapdoor and RH trapdoor profile with
plunger.
Fit the top guides and secure to the wall /
ceiling.
Fit the upper control tubes/trays.
Thread trailing cables up into the control
tubes/trays and attach chain
Make sure Rubber Pad is in Catch Tank and fit
the Ram as instructed in manual. (Check
direction of bleed ports line up with holes in
guides)
Attach the chain to the rear of the sling and then
fit the sling and bolt up the rollers (lateral, mid
and top).
Fit bolt through head of ram. Ensure spacer in
head of ram)
Bleed the ram.