EasyManua.ls Logo

Trane S Series - Completion Check Sheet and Request for Trane Service; Model RTWD Chiller Installation

Trane S Series
100 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
RLC-SVX09Q-EN
93
Model RTWD Chiller Installation
Completion Check Sheet and
Request for Trane Service
Important: A copy of this completed form must be
submitted to the Trane service agency that will
be responsible for the start-up of the chiller.
Start-up will NOT proceed unless applicable
items listed in this form have been
satisfactorily completed. See unit IOM RLC-
SVX09*-EN for detailed installation
instructions.
To:
Trane Service Office:
S.O. Number:
Serial Numbers:
Job/Project Name:
Address:
The following items
are being installed
and will be completed by:
Important: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane®
products. Contractor shall provide Trane (or an
agent of Trane specifically authorized to
perform start-up) with notice of the scheduled
start-up at least two weeks prior to the
scheduled start-up.
Important: It is required that heaters are energized for a
minimum of 24 hours prior to start-up.
Therefore, chiller should have power for
this amount of time before Trane Service
arrives to do start-up.
Check boxes if the task is complete or if the answer is
“yes”.
1. Screw Chiller
☐ Installation meets foundation requirements
☐ In place and piped.
☐ Isolation pads or isolators installed.
2. Piping
☐ Chilled water piping connected to:
☐ Evaporator
☐ Air handling units
☐ Pumps
☐ Flow switch or flow proving device installed (if
not factory provided)
☐ Strainer installed and cleaned
☐ Drain and vents in both evaporator waterboxes
are piped with shutoff valve, or plugs have been
reinstalled.
☐ Condenser piping connected to:
☐ Condenser
☐ Pumps
☐ Flow switch or flow proving device installed (if
not factory provided)
☐ Condenser water regulating valve
☐ Cooling tower
☐ Drain and vents in both condenser waterboxes
are piped with shutoff valve, or plugs have been
reinstalled.
☐ Make-up water connected to cooling water.
☐ Water supply connected to filling system
☐ Does unit have freeze inhibitor? If unit has freeze
inhibitor:
☐ Verify type and concentration correct per unit
submittal
☐ Calculate and record freeze point of the
solution: __________
☐ Systems filled
☐ Pumps run, air bled from system
☐ Strainer installed in entering water piping
(evaporator and condenser) and cleaned
☐ Relief valve ventilation piping installed
3. Flow balancing valves installed
☐ Leaving chilled water
☐ Leaving condenser water
☐ Proper porting to measure flow and balance
4. Gauges, thermometers, and air vents
☐ Installed on both sides of evaporator
☐ Installed on both sides of condenser and heat
recovery condenser (as applicable)
5. Wiring
☐ Wire size per submittal and NEC 310-16
☐ Full power available
☐ External interlocks (flow switch, pumps auxiliary,
etc.)
☐ Chilled water pump (connected and tested)
☐ Condenser water pump (connected and tested)
☐ Cooling tower fan rotation checked
☐ Separate power sources available for 220V water
regulating valve, if selected
☐ 115 Vac power available for service tools as
required
☐ All controls installed and connected
Log and Check Sheets

Table of Contents