RLC-SVX09Q-EN
93
Model RTWD Chiller Installation
Completion Check Sheet and
Request for Trane Service
Important: A copy of this completed form must be
submitted to the Trane service agency that will
be responsible for the start-up of the chiller.
Start-up will NOT proceed unless applicable
items listed in this form have been
satisfactorily completed. See unit IOM RLC-
SVX09*-EN for detailed installation
instructions.
To:
Trane Service Office:
S.O. Number:
Serial Numbers:
Job/Project Name:
Address:
The following items
are being installed
and will be completed by:
Important: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane®
products. Contractor shall provide Trane (or an
agent of Trane specifically authorized to
perform start-up) with notice of the scheduled
start-up at least two weeks prior to the
scheduled start-up.
Important: It is required that heaters are energized for a
minimum of 24 hours prior to start-up.
Therefore, chiller should have power for
this amount of time before Trane Service
arrives to do start-up.
Check boxes if the task is complete or if the answer is
“yes”.
1. Screw Chiller
☐ Installation meets foundation requirements
☐ In place and piped.
☐ Isolation pads or isolators installed.
2. Piping
☐ Chilled water piping connected to:
☐ Evaporator
☐ Air handling units
☐ Pumps
☐ Flow switch or flow proving device installed (if
not factory provided)
☐ Strainer installed and cleaned
☐ Drain and vents in both evaporator waterboxes
are piped with shutoff valve, or plugs have been
reinstalled.
☐ Condenser piping connected to:
☐ Condenser
☐ Pumps
☐ Flow switch or flow proving device installed (if
not factory provided)
☐ Condenser water regulating valve
☐ Cooling tower
☐ Drain and vents in both condenser waterboxes
are piped with shutoff valve, or plugs have been
reinstalled.
☐ Make-up water connected to cooling water.
☐ Water supply connected to filling system
☐ Does unit have freeze inhibitor? If unit has freeze
inhibitor:
☐ Verify type and concentration correct per unit
submittal
☐ Calculate and record freeze point of the
solution: __________
☐ Systems filled
☐ Pumps run, air bled from system
☐ Strainer installed in entering water piping
(evaporator and condenser) and cleaned
☐ Relief valve ventilation piping installed
3. Flow balancing valves installed
☐ Leaving chilled water
☐ Leaving condenser water
☐ Proper porting to measure flow and balance
4. Gauges, thermometers, and air vents
☐ Installed on both sides of evaporator
☐ Installed on both sides of condenser and heat
recovery condenser (as applicable)
5. Wiring
☐ Wire size per submittal and NEC 310-16
☐ Full power available
☐ External interlocks (flow switch, pumps auxiliary,
etc.)
☐ Chilled water pump (connected and tested)
☐ Condenser water pump (connected and tested)
☐ Cooling tower fan rotation checked
☐ Separate power sources available for 220V water
regulating valve, if selected
☐ 115 Vac power available for service tools as
required
☐ All controls installed and connected
Log and Check Sheets