Flue gas installation
Installation and maintenance instructions ecoTEC plus 0020116700_01 27
7
Location
Minimum
dimensions
A
Directly below an opening, air brick, opening win-
dows, etc.
300mm
B Above an opening, air brick, opening window, etc. 300mm
C
Horizontally to an opening, air brick, opening win-
dow, etc.
300mm
D
Below temperature-sensitive building components
e.g. plastic gutters, soil pipes or drain pipes
75mm
E Below eaves 200mm
F Below balconies or car port roof 200mm
G From a vertical drain pipe or soil pipe 150mm
H From an internal or external corner 200mm
I Above ground, roof or balcony level 300mm
J From a surface facing the terminal 600mm
K From a terminal facing the terminal 1200mm
L
From an opening in the car port (e.g. door, win-
dow) into the dwelling
1200mm
M Vertically from a terminal on the same wall 1500mm
N Horizontally from a terminal on the same wall 300mm
O From the wall on which the terminal is mounted N/A
P From a vertical structure on the roof N/A
Q Above intersection with roof 300mm
7.1 Position of the termination in a fan-assisted air/flue gas
duct
BS5440–1 It is recommended that the fanned flue terminal
should be positioned as follows:
a) at least 2 m from an opening in the building directly
opposite, and
b) so that the products of combustion are not straightly
directed to discharge across a boundary.
1) Dimensions D, E and F:
These clearances may be reduced to 25mm without
affecting the performance of the boiler. In order to
ensure that the condensate plume does not affect
adjacent surfaces the terminal should be extended as
shown in ¬fig.7.6.
2) Dimension H:
This clearance may be reduced to 25mm without
affecting the performance of the boiler. However, in
order to ensure that the condensate plume does not
affect adjacent surfaces a clearance of 300mm is pre-
ferred. For IE, recommendations are given in the cur-
rent edition of IS813.
For 1 and 2 above you can use the Variable Termination Kit
to move the termination point away from the building fab-
ric.
Article numbers:
0020060584 - White
0020060585 - Black
7.6 Termination of air/flue gas duct under balcony or eaves