Appendix
vatech A9 (Model: PHT-30CSS) Installation Manual A-9
4. Before Installation:
Site Check List
Yes No
Is the room large enough?
At minimum,
with CEPH unit: 2,200 mm x 2,200 mm x 2,600 mm /
87” x 87” x 103.
Without CEPH unit: 2,200 mm x 1,400 mm x 2,600 mm / 87” x
55” x 103”
Is the door entrance wider than 800 mm (32”)?
Is a radiation protection plan in place?
Do equipment and PC use the same dedicated circuit?
Does the electrical input condition to the installation site meet
the MEIGaN requirements?
Is the local network IP address of clinic 192.168.33.xx?
Is a compressor or air conditioner suction located right next to
X-ray Room?
Is the floor flat and level?
Is the carpet on the floor? If so, remove it.
Before Opening Boxes
Yes No
Did the delivery company carry and handle with caution?
Did the installers take pictures of boxes before opening them?
Did the installer make sure there are not any suspicious holes
or scratches on the box?
Is the ShockWatch indicator red?
Is the TiltWatch indicator red?