EasyManuals Logo

Vatech A9 Installation Manual

Vatech A9
162 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #157 background imageLoading...
Page #157 background image
Appendix
vatech A9 (Model: PHT-30CSS) Installation Manual A-9
4. Before Installation:
Site Check List
Yes No
Is the room large enough?
At minimum,
Without CEPH unit :
2,500 mm (L) x 1,700 mm (W) x 2,700 mm (H)
With CEPH unit :
2,500 mm (L) x 2,500 mm (W) x 2,700 mm (H)
Is the door entrance wider than 800 mm (32”)?
Is a radiation protection plan in place?
Do equipment and PC use the same dedicated circuit?
Does the electrical input condition to the installation site meet
the MEIGaN requirements?
Is the local network IP address of clinic 192.168.33.xx?
Is a compressor or air conditioner suction located right next to
X-ray Room?
Is the floor flat and level?
Is the carpet on the floor? If so, remove it.
Before Opening Boxes
Yes No
Did the delivery company carry and handle with caution?
Did the installers take pictures of boxes before opening them?
Did the installer make sure there are not any suspicious holes
or scratches on the box?
Is the ShockWatch indicator red?
Is the TiltWatch indicator red?

Table of Contents

Other manuals for Vatech A9

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vatech A9 and is the answer not in the manual?

Vatech A9 Specifications

General IconGeneral
BrandVatech
ModelA9
CategoryMedical Equipment
LanguageEnglish

Related product manuals